Project Location

Fisher Creek Trail Phase 1, from W. Court Street to Dartmouth Drive (segment in pink)

Fisher Creek Trail Phase 1 Map

Project Description

The City of Janesville and the Wisconsin Department of Transportation propose constructing a 10-foot-wide paved off-road trail with an approximate project length of 0.80 miles. The alignment will start at the existing path north of W. Court Street along Austin Road and travel north to Dartmouth Drive. This project will also include a trail connection to Greenway Point Drive. The entire project will be located within the City’s greenbelt and right of way.

The City was successful in obtaining WisDOT Transportation Alternatives Program (TAP) funding. 

  • Safety improvements will be made at the Mineral Point Avenue trail crossing.
    • Construct a pedestrian refuge safety island
    • Provide a streetlight near the crossing
    • Install fluorescent bike/pedestrian signs
    • Add pavement markings

Project Documents and Information

2024 Community Engagement Forum Materials:  February 28, 2024

Schedule

  • Begin Design:  August 2023
  • Survey and Wetland Delineation:  September 2023
  • Community Engagement Forum:  February 2024
  • Completed Environmental Review and Preliminary Design:  May 2024
  • Complete Final Design:  September 2024
  • Local Project Bidding:  November 2024
  • Start Construction:  Summer 2025

Contact Information

Thomas Ballweg, P.E.
 Senior Engineer
 Phone:  (608) 373-6070